Dangote Petroleum Refinery is extending the maintenance window for its core processing units, delaying the facility’s highly anticipated ramp-up to full capacity.
CEO David Bird confirmed in a press briefing that critical work remains ongoing on the Residue Fluid Catalytic Cracker (RFCC) and the Crude Distillation Unit (CDU), two pillars of the 650,000 barrel-per-day (bpd) complex.
While the extension may trigger short-term supply anxiety in West Africa, management has framed the downtime as a “de-bottlenecking” exercise. If successful, the upgrades are expected to boost the refinery’s nameplate capacity by 7% to 700,000 bpd, cementing its position as the largest single-train refinery in the world.
The RFCC Bottleneck: Gasoline Yields Under Pressure
The RFCC—the “engine room” that converts heavy residue into high-value gasoline—has been the primary source of operational friction:
-
Restart Pushed Back: Initially expected to return online earlier, analysts at Kpler now project the RFCC restart for February 10, with the potential for further slippage into late February.
-
Production Cap: Persistent technical issues with the unit have capped gasoline output, forcing the refinery to rely on its “reformer” unit for lower-volume petrol production in the interim.
-
Importing Intermediate: To keep conversion units loaded during the outage, the refinery has been importing intermediate feedstocks—a move Bird defended as standard merchant refining practice rather than “fuel importation.”
CDU Upgrade: Racing for the 700,000 bpd Milestone
The maintenance on the Crude Distillation Unit is more than just a routine check; it is a capacity play:
-
The 700k Target: The current turnaround aims to remove design constraints, allowing the CDU to exceed its 650,000 bpd design margin.
-
Full-Capacity Tests: Bird announced that the refinery will begin performance test runs at full capacity this month (February 2026), marking a key transition toward steady-state operations.
-
Insurance Pivot: While currently insured at 650,000 bpd, the refinery plans to engage the insurance market to raise that limit once the 700,000 bpd threshold is proven.
Market Impact: Regional Supply and Price Stability
The extension of planned works has ripple effects across the Nigerian and European fuel markets:
-
Logistics Warning: Amid the maintenance, the refinery warned that continued dependence on “coastal logistics” (shipping fuel via sea rather than land/pipeline) could push petrol pump prices toward ₦1,000 per litre.
-
European Inflow: Traders are already positioning for tighter regional supply, with an influx of European gasoline expected to fill any temporary gaps in West African deliveries.
-
2026 Outlook: Despite the delay, the refinery maintains its 2026 target of sustaining full nameplate capacity, aiming to provide up to 57 million litres of petrol daily once the “bugs” are ironed out.